Slab Strengthening for Service Penetrations – A Hotel
Slab Strengthening for Service Penetrations – A Hotel

Request more information

Project Details

Project: Premier Inn Hotel London

Client: Barnes Construction

Contract Duration: 4 weeks

Scope of Works: Carbon Fibre slab strengthening for penetrations.

An office to hotel conversion in Kingston Upon Thames was the project for Barnes Construction from Suffolk. The original 1960’s concrete framed building in the town centre had quite restrictive head room between slabs. We were contacted by the clients consulting engineers to help with the transfer of loads through the slabs due to cutting of the reinforcement through drilling service holes.

If you would like to request more information, please fill out the contact form.

How to Fix Leaks in Concrete WallsBlogConcrete Repairs & Specialist Work DivisionHydrophobic & Hydrophilic Leak SealingStructural Rehabilitation and Repair
May 9, 2023

How to Fix Leaks in Concrete Walls

A brief guide on how to fix leaks in concrete walls, including the cause of leaking in concrete and how to detect leaks Knowing the…
The Pros and Cons of Blast CleaningBlogSprayed Concrete Services
May 9, 2023

The Pros and Cons of Blast Cleaning

We detail the pros and cons of blast cleaning as a surface preparation technique - from classic types like abrasive and wet blasting to an…
The pros and cons of using concrete crack resin injection for repairsBlogConcrete Repairs & Specialist Work DivisionCrack Injection SystemsSprayed Concrete Services
March 14, 2023

The pros and cons of using concrete crack resin injection for repairs

A brief guide to concrete crack resin injection services in the UK It’s common for concrete buildings and structures to need revisiting and repairing –…