Project: Blyth Road – Hayes
Client: CField Construction
Contract Duration: 24 weeks
Scope of Work: Strengthening of an existing concrete frame under construction for mixed use development, 300 areas strengthened using Tyfo Fibrwrap Systems.
Strengthening of an existing concrete frame under construction for mixed use development, more than 300 individual areas strengthened using Tyfo Fibrwrap
Systems. The strengthening for flexure and punching shear throughout these 3 large buildings took more than 20 weeks. A final coating of Fibrwrap’s 4 hour Fire Protection Coating was applied to every area.