Project: Humber Power Station

Client: SHB Power

Contract Duration: 4 days

Scope of Work: Repair and strengthening of Cooling water inlet pipes from scouring and erosion using Tyfo Fibrwrap FRP systems and Tyfo specialist under
water epoxy

South Humber Bank Power Station (SHB) had a leak remediation and strengthening issue on their cooling water intake pipes. During a planned shutdown CCUK carried out extensive internal repairs, leak sealing and carbon fibre strengthening to these critical pieces of infrastructure.

If you would like to request more information, please fill out the contact form.

Coffee & Catch-up with CCUK BlogCCUK News
October 12, 2021

Coffee & Catch-up with CCUK

We’ve got some brilliant news to share – our full team is back in the office, which means face-to-face client meetings can resume! Our structural…
Different Types of Corrosion in Offshore Structures BlogCarbon Fibre Strengthening
October 11, 2021

Different Types of Corrosion in Offshore Structures

Types of corrosion in offshore structures & the best marine corrosion inhibitors explained Corrosion is a number one cause of deterioration in buildings and structures…
Your Quick Guide to Abrasive and Sponge Jet Blasting BlogSurface Preparations
October 11, 2021

Your Quick Guide to Abrasive and Sponge Jet Blasting

What is abrasive and sponge jet blasting used for? Abrasive blasting is a reliable, effective method of cleaning and preparing surfaces – it’s as old…