Project Details

Project: Pier Protection – Phase II

Client: Bristol Port Company

Contract Duration: 8 weeks

Scope of Works: Coastal Protection works of two concrete pier support columns dimensions 10m high x 3m wide by 1m thick.

Due to the great success in 2012 when we provided coastal erosion protection to 3 x smaller support columns, Bristol Port Company immediately saw the value in extending the life of these vital support columns at the entrance to the port at Avonmouth. The pier columns when cast where considerably larger than the reduced size of 10m high, 3m wide and 1m thick. To ensure no further erosion we wrapped these columns with Tyfo Systems epoxy.

If you would like to request more information, please fill out the contact form.

How to Strengthen Weak Concrete Columns: Including Our Top 3 Methods BlogCarbon Fibre StrengtheningConcrete Repairs & Specialist Work Division
July 28, 2021

How to Strengthen Weak Concrete Columns: Including Our Top 3 Methods

How to strengthen concrete columns? Column strengthening is a process within concrete repairs that involves adding or restoring to the `load capacity`, or how much…
'Concrete Goals' by Business Works Magazine Blog
July 23, 2021

‘Concrete Goals’ by Business Works Magazine

Composites Construction UK (CCUK) founder Jamie Dempster is targeting the Humber and M62 energy corridor with his expanded range of structural repair services. He talks…
Top 3 Pipe Rehabilitation Methods BlogPipeline & Liquid Storage
July 19, 2021

Top 3 Pipe Rehabilitation Methods

Which pipe rehabilitation method should I choose? Pipe rehabilitation is common practice for ageing pipelines or those that have carried large volumes of liquid repeatedly,…