Project: Royal Portbury Dock
Client: Bristol Port Authority
Contract Duration: July/August 2012
Scope of Works: Repair and Protection of the West Stub Pier support columns
The erosion process caused by the sea had reduced the columns to approximately the size they should have been at construction. In addition the shape and size of the columns had become very irregular. The initial brief from the client was that they had assumed the columns were suitable in size and strength however they required protection from any further coastal erosion.
Composites Construction UK (Fibrwrap) has provided a solution to repair and protect these columns using unique solutions of TYFO Fibrwrap Systems.