Project: Merchant Taylor School
Client: Borras Construction
Contract Duration: 2 weeks
Scope of Works: Slab strengthening against punching shear.
Merchant Taylor School in Northwood London is an independent day school for boys that was first established in 1561. Borras were awarded the contract to construct a new two-storey building and work began on site in March 2014. CCUK was employed by Borras to rectify a lack of reinforcement at eight locations over columns in a slab within the existing building in December 2014. Three layers of carbon fibre fabric was designed an applied by CCUK (Fibrwrap) to the top of the slab in both directions at each column location.