STRENGTHENING OF REINFORCED CONCRETE SLABS, BEAMS, COLUMNS AND SHEAR WALLS

Duration:

6 Weeks

Project Details

Scope of Work: Working closely with the structural team CCUK designed and installed an exact and complexed combination of both CFRP, Shear Bolting and steel, providing a Hybrid Solution for a multi-faceted strengthening solution.

The Challenge

There was a significant increase of imposed loads on the existing structure due to an extension adding additional stories and bedrooms to the Hotel. Strengthening was required to existing columns, shear walls, beams for hogging and sagging in addition to slabs for punching shear. The hotel remained live during the strengthening works which included working in closed rooms, corridors, restaurants and service kitchens.

The Solution

This was a complexed structural refurbishment project, requiring close working with the designer and main contractor C-Field Construction.

Columns in the existing restaurant were strengthened for additional axial load by adding hoop layers of Fibrwrap carbon fibre strengthening system, the final application had a 2hr fire protection system before decorative finishes.

Shear walls were strengthened with CFRP within the fire exit stairs and existing restaurant for additional vertical loadings and a new opening through.

Beams within bedrooms and live corridors were strengthened using the carbon fibrewrap system, works were carried out in the live hotel with control measures in place.

Punching Shear strengthening was attempted using stainless steel shear rods but due to the congestion of the reinforcement within the slab CCUK specifically designed a carbon fibre solution in conjunction with WSP Consulting Engineers. CCUK also manufactured and installed the shear brackets to column/slabs in several bedroom areas.

CCUK, used the analysis done by the engineer to design a Fibrwrap CFRP and steel ‘Hybrid’ strengthening system. The subsequent ‘design strategy’ enabled the successful application of our solution in all affected areas, whilst the hotel remained fully functional.

The Result

CCUK delivered another quality project for two of our top clients, on time and to budget. We would like to thank Graham Construction and HTS for their continued, ongoing support.

Download our Project Insider
Download Here >
Structural Strengthening Design for Concrete Structures UK: A Technical GuideBlog
May 19, 2026

Structural Strengthening Design for Concrete Structures UK: A Technical Guide

The perceived necessity of decommissioning compromised concrete assets often obscures the technical viability of advanced intervention, representing...
Advanced Masonry Reinforcement Techniques UK: A Technical Guide to Structural RemediationBlog
May 18, 2026

Advanced Masonry Reinforcement Techniques UK: A Technical Guide to Structural Remediation

The traditional reliance on reactive crack-stitching is no longer sufficient to meet the rigorous demands of the second-generation Eurocode 6...
A Technical Guide to Resin Injection: Structural Remediation and Leak SealingBlog
May 15, 2026

A Technical Guide to Resin Injection: Structural Remediation and Leak Sealing

The long-term viability of critical infrastructure is frequently dictated by the precision of chemical interventions at the molecular level, where...