SHEAR WALL STRENGTHENING

Duration:

24 Weeks

Project Details

Scope of Work: An 11 storey office block in North London was converted into luxury residential apartments in 2015. CCUK (Fibrwrap) was contracted to design and install CFRP wall strengthening in the central cores for additional loading, door openings through shear walls internally and service risers through concrete slabs.

The Challenge

Adding 2 additional stories to this already high-rise structure in North London gave the structural engineer some real headaches. The three central concrete cores provide the main stability for the structure and adding the extra loads was resulting in some hefty new stresses. In addition, the requirement of openings through floor slabs and shear walls were also required to suit the new layouts for the refurbishment.

The Solution

The first job was to attack the crack repairs, with cracks in both directions all the way through the balconies. It was decided to strengthen across the cracks perpendicular using NSM (near surface mounting) of Tyfo Carbon Fibre Plates. Narrow grooves were cut into the substrate at set centres on both the top and also The whole project consumed over 4000m2 of Fibrwrap Carbon Fibre Wrap Systems, 32 tonnes of steel and over 300 Fibrwrap patented carbon fibre anchors to pass through slabs and staircases between floors. In addition the design called for the strengthening scheme within the cores to be anchored into the foundations, CFRP anchors 1.6m long were drilled and resin fixed into the pile caps.

The Result

This extremely complicated FRP design could only be achieved using Tyfo Fibrwrap Systems, we were very proud to be working on such a large project and believe is still the largest FRP strengthening of a building in the UK to date.

Download our Project Insider
Download Here >
How to Strengthen a Concrete Slab: A Technical Guide to Structural Life-ExtensionBlog
May 29, 2026

How to Strengthen a Concrete Slab: A Technical Guide to Structural Life-Extension

The assumption that structural degradation or a change in occupancy necessitates the wholesale demolition of a concrete slab is an engineering...
Blast Mitigation Systems UK: Advanced Structural Protection for Critical InfrastructureBlog
May 28, 2026

Blast Mitigation Systems UK: Advanced Structural Protection for Critical Infrastructure

What if the most effective method for hardening critical infrastructure against explosive threats isn't adding mass, but rather increasing ductility...
Blog
May 27, 2026

Stadium Structural Strengthening in the UK: A Technical Guide to Asset Life-Extension

Could the structural integrity of a fifty-year-old concrete terrace reliably support the intensified dynamic loads of a modern, safe-standing crowd...