Column Repair and Strengthening - Northumberland
Column Repair and Strengthening - Northumberland

Request more information

Project Details

Project: Bridge Repair and Strengthening Works A69

Client: Roadlink A69

Contract Duration: 10 days

Scope of Works: Concrete repair and protection with Fibre Reinforced polymers

12 bridge pier columns required concrete repairs and protection on the busy A69 in Northumberland. The piers were excavated to a depth of 0.5m below ground level. They were then cleaned and repaired using traditional concrete repair techniques. A long term protection system using Fibrwrap Systems (Fibre Reinforced Polymers) was then applied to the bottom 2m of the pier columns to protect from external corrosion and delamination.

If you would like to request more information, please fill out the contact form.

Coffee & Catch-up with CCUK BlogCCUK News
October 12, 2021

Coffee & Catch-up with CCUK

We’ve got some brilliant news to share – our full team is back in the office, which means face-to-face client meetings can resume! Our structural…
Different Types of Corrosion in Offshore Structures BlogCarbon Fibre Strengthening
October 11, 2021

Different Types of Corrosion in Offshore Structures

Types of corrosion in offshore structures & the best marine corrosion inhibitors explained Corrosion is a number one cause of deterioration in buildings and structures…
Your Quick Guide to Abrasive and Sponge Jet Blasting BlogSurface Preparations
October 11, 2021

Your Quick Guide to Abrasive and Sponge Jet Blasting

What is abrasive and sponge jet blasting used for? Abrasive blasting is a reliable, effective method of cleaning and preparing surfaces – it’s as old…