Project Details

Project: Column Strengthening with Carbon Fibre

Contract Duration: 2 Weeks

Scope of Work:  To significantly add capacity to the ground floor columns of this 8 storey building whilst causing minimum disruption to the live reception area and keeping the geometry of the columns as small as possible.

CCUK provided an innovate structural solution as an alternative option to traditional methods that would have been time consuming and difficult to execute due to congestion of other buildings in the surrounding area.

If you would like to request more information, please fill out the contact form.

CFRP Bridge Strengthening for Steel Bridge GirdersBlog
October 22, 2026

CFRP Bridge Strengthening for Steel Bridge Girders

A steel girder can gain structural capacity without the added dead load associated with conventional steel reinforcement. CFRP bridge strengthening...
Structural Strengthening Feasibility: Retrofitting and Rehabilitation OptionsBlog
October 21, 2026

Structural Strengthening Feasibility: Retrofitting and Rehabilitation Options

A structure that can no longer safely meet its intended demands may need strengthening rather than replacement. Structural strengthening improves the...
Long-term performance of FRP systems: what affects itBlog
October 20, 2026

Long-term performance of FRP systems: what affects it

Corrosion resistance alone doesn’t determine the long-term performance of FRP systems. Fibre, matrix and fibre-matrix interface properties all...