CARBON FIBRE STRENGTHENING

Duration:

3 Months

Project Details

Scope of Work: Working on behalf of some large contractors and very closely with Wolverhampton Council, CCUK has designed Carbon Fibre Strengthening solutions to enable the refurbishment of the HRRB’s for electrical, mechanical and sprinkler installation.

CCUK is currently carrying out carbon fibre design and installation on 7 different projects on the £100 million pound development including Heath Town Estate, phase one of the works is expected to take 3 months.

The Challenge

The new services that need to be installed in the high-rise residential blocks mostly travel through the communal areas (landings and corridors) and these spaces are very limited in terms of space and ceiling height. As the floor slabs need to have riser holes cut through them, the original structural design of the building is compromised as reinforcement is lost. Coupled with working in a live building and in very small spaces traditional strengthening measures would be even more problematic.

The Solution

CCUK’s expert composite design team, working closely and in conjunction with the councils’ structural engineering team designed an effective carbon fibre strengthening system to transfer forces and provide the stability required due to the cutting of existing reinforcement in the building.

The solution result is a very quick and effective carbon fibre wrap solution, designed to be installed around the cores prior to cutting, also the innovative use of the patented ‘Tyfo Fibre Anchor System’ for providing additional anchorage in such tight spaces.

Our team of fully trained installers have carried out the removal of existing floor screeds, temporary works, installation of the composite strengthening system and replacement of the screed. All safety measures have been kept within CCUK’s remit to ensure the safest possible environment for the tenants still living in the buildings.

The Result

Carbon fibre wrap systems are extremely strong, light and thin. Working in very tight spaces and with restricted head height meant that using these 1mm thick strengthening systems was the most innovative construction method possible. Within one particular building 22 storeys were strengthened in just 3 days, at a maximum 3mm thick overall no loss of coverage with the screeds and head height makes these systems perfect for such projects.

Tyfo fire protection systems have been used as a fire protection coating for the carbon fibre strengthening system on the soffits.

Download our Project Insider
Download Here >
Bridge Nosing Systems: A Technical Guide to Specification and Remediation (2026)Blog
May 13, 2026

Bridge Nosing Systems: A Technical Guide to Specification and Remediation (2026)

With 2,928 council-maintained bridges in Great Britain currently classified as substandard and a maintenance backlog estimated at £5.8 billion, can...
The Role of a Specialist Engineering Contractor in Structural Life-ExtensionBlog
May 12, 2026

The Role of a Specialist Engineering Contractor in Structural Life-Extension

With the UK infrastructure sector projected to grow by up to 3.9% in 2026 whilst private housing contracts, the strategic focus for asset managers...
Structural Repairs: A Technical Guide to Asset Remediation and Life-ExtensionBlog
May 11, 2026

Structural Repairs: A Technical Guide to Asset Remediation and Life-Extension

The decision to decommission a degrading asset is frequently a failure of engineering strategy rather than a terminal material exhaustion. With the...