Project: Hoares Bank
Client: Vinci Construction
Contract Duration: 12 weeks
Scope of Works: Slab strengthening with Tyfo SCH Systems to meet current office loadings and allow the retainment of listed facades.
This 1904 office building was being refurbished for the administration department of a private bank in London’s Fleet Street. Composites Construction UK designed and installed the Tyfo Fibrwrap Carbon Fibre Strengthening system to achieve the clients requirements. The design was for two layers of our SCH systems applied in double thickness at 300mm width strips at 600mm centres. This application allowed the effective design and install of all M&E services.